Construction Timeline
Estimated Construction Timeline
|
Estimated Start |
Completion |
Site development |
Spring 2006 |
Spring 2008 |
Hospital |
Spring 2006 |
Early 2009 |
Residence Hall |
Summer 2005 |
Completed in Fall 2006 |
Psychiatric Research Institute |
Summer 2006 |
Late 2008 |
West Central Energy Plant |
Spring 2006 |
Fall 2007 |
Parking deck |
Spring 2006 |
Early 2009 |
Jones Eye Institute expansion |
Fall 2004 |
Completed in Spring 2006 |
ACRC expansion |
Summer 2007 |
2010 |
Education Building |
Summer 2007 |
Summer 2008 |
(All dates
subject to change)
Click here for a history of UAMS expansion.
|
 |