Budget Maintenance
Departments may refine and correct their original budgets at any point during
the fiscal year through the Budget Revision process. The form used to initiate
these changes is called the “Request for Budget Revision”, and it
is available online as a link from this website and can also be emailed to users
by Budget Office staff.
The “Request for Budget Revision” form consists of the initial
page and a continuation page. This latter is needed only when the revisions are
so extensive that they require multiple pages. The data required on the initial
page includes the preparer’s name, telephone number and slot number, date
of preparation, the purpose of the revision, and a brief statement of explanation.
The body of the revision is made up of numerically sequenced lines that detail
the changes requested and their distribution by month. Each line must include
a Fund, Commitment Item, Fund Center, and a dollar amount related to either a Reduction
or an Increase in budget. The information on these lines should reflect as accurately
as possible the financial activity that is planned. All requests must maintain
a balanced budget, and therefore the total reductions included on the revision
must equal total increases.
Each budget revision is restricted to a single fund. Therefore, if the change
requested involves a transfer between funds, separate budget revision numbers
will be assigned.
If the Request for Budget Revision requires the transfer of fund balance, or
requires the transfer of budget between funds with the change to be reflected
in actual revenue/expenditures, then an Interdepartmental Transfer form (IDT)
must also be completed by the requesting department. The original IDT is sent
to the UAMS Finance Department, and a copy should be attached to the submitted
budget revision form.
When the balanced request is completed and contains the appropriate signatures,
it should be forwarded to the Budget Office at
mailbox #633.
|